Driven Pile Capacity Assessment Using Installation Energy and Pile Set-Up

Matt Neale, Kasgin Banab, Darren Beaumont, Kelsey Wierenga, Tim van der Wal

Dans les comptes rendus d’articles de la conférence: GeoVirtual 2020: 73rd Canadian Geotechnical Conference

ABSTRACT: This paper describes the process used to verify ultimate pile capacity for a wharf project in Kitimat, British Columbia, Canada. The wharf is in a fjord system, where the Kitimat River meets the Douglas Channel, with a deep foundation supported by open-ended steel pipe piles. The stratigraphy primarily consists of interbedded sands, silty sands, silts and clays. The assessment process first uses hammer energy and penetration per blow to estimate end-of-initial-drive (EOID) pile capacity, based on high strain dynamic testing and static load testing. Then an appropriate set-up factor is applied to the EOID capacity to estimate the long-term capacity of a pile. Set-up refers to the increase of pile capacity over time and is mostly caused by excess porewater pressure dissipation, which is primarily by geology and pile type.


Please include this code when submitting a data update: GEO2020_254

Retrouver cet article:
Les membres de la Société canadienne de géotechnique peuvent accéder à cet article, ainsi qu'à tous les autres articles de la Conférence Géotechnique Canadienne, dans le Espace membre. Les comptes rendus d'articles sont également disponibles dans de nombreuses bibliothèques.

Citer cet article:
Neale, Matt, Banab, Kasgin, Beaumont, Darren, Wierenga, Kelsey, van der Wal, Tim (2020) Driven Pile Capacity Assessment Using Installation Energy and Pile Set-Up in GEO2020. Ottawa, Ontario: Canadian Geotechnical Society.

@article{Neale_GEO2020_254, author = Matt Neale, Kasgin Banab, Darren Beaumont, Kelsey Wierenga, van Tim der Wal,
title = Driven Pile Capacity Assessment Using Installation Energy and Pile Set-Up ,
year = 2020
}